Q: What is a Cost Plan?
A
schedule showing how much of a developer’s budget is to be spent on each
element of his project so that the design and construction can be controlled
within the forecast.
Q: Purpose of Cost planning process is mainly
divided into three parts
• To set a realistic cost limit
• To decide how the money is to be spent
• To check that the money is being spent as intended.
Q: Preliminaries estimates
• This is prepared to enable the clients to understand his financial
commitments at the early stage of the project
• Also enables the designer to design within the available budget in a
controlled manner.
Q: Different methods of preliminary estimates
• Conference estimate
• Financial methods
• Unit method
• Superficial method
• Cube method
• Storey enclosure method
• Elemental method (this is an extension of superficial method)
• Approximate quantity method.
Q: Different elements of a building - For cost
planning purpose
• Substructure
• Superstructure
• Internal finishes
• Fittings and furnishings
• Services
• External works
• Preliminaries
• Contingencies
Q: How to prepare Cost Plan for a project from
cost plans of existing projects –
By
adjusting time, quality, fluctuation, location factors.
Q: Cost Value reconciliation (CVR) –
This is a
format used to compare actual cost against valuation on a project specific
basis. This is to bring together the established totals for cost and value to
illustrate the profitability of a company. Its intention is to ensure that the
profits shown in company accounts are accurate and realistically display the
current financial position. CVR provides close control over project cost, company
provisions and overheads, and value earned.
Its
purposes are,
• Statutory requirements or for audit purpose (Only in some countries
like UK)
• To get information which can have a direct impact on a company
management.
• To identify the potential problems or critical elements of a contract.
Q: At what stage of a project you will prepare a
cost plan? Would you still use it when the project is underway?
Cost plan
is prepared in the beginning of the project before issuing tender.
Yes. If
it was identified later that there was flaws in the design leading to
uneconomic construction and the Construction has not progressed beyond the
alteration stages, but the Net Saving potential is considerably reduced with
Time. VE is to be preferably done initially when there is a better chance of identifying
& overcoming Potential problems at an early stage thus giving better value
for money.
Q: What are the stages of design of a project?
Concept
Schematic
Detailed
design
Q: Some terms in Cost Value management –
• BCWP – Budgeted Cost of Work Performed
• BCWA – Budgeted Cost of Work accomplished.
• BCWS – Budget Cost Work Scheduled.
• ACWP – Actual Cost of Work Performed
• ACWA – Actual cost of work accomplished.
• CPI – Cost Performance Index = EV / AC (Earned Value / Actual Cost)
should be above 1
• VAC – Value At completion.
• EAC – estimate at completion (projection of total cost to complete the
work)
Q: Difference between Cost Management and Value
Management –
• CM focuses on issues like estimation and budgeting, cash flow
management, cost control.
• VM focuses on Optimizing project value
Q: Type of cost control techniques.
• Budget monitoring system
• Cost coding system
• Earned Value Management
• Network analysis.
Q: Earned Value Management (EVM) –
It is a
project management technique for measuring project progress in an objective
manner. EVM will combine measurements of scope, schedule and Cost in a single
integrated system. This will provide an early warning of performance problems. It
is the management of value of the work actually accomplished at the cost rates
set out in the original budget. EVM information provides the efficiency with
which the budgeted money is used relative to realized value. This helps to
forecast estimated cost and schedule to the project completion.
Q: Earned Value –
Is a
concept used to express the progress of a project in terms of financial value.
(Eg. If I have completed half of a project valued one million, I can say that I
have earned Dhs.500,000. in fact the real current value may be nothing since no
benefit can be generated from a half completed project.)
Source: J Thomas (July 2010)
No comments:
Post a Comment